A rejected batch of electrodes is expensive. A rejected batch discovered after the welds are made is far more expensive. The checks below take about fifteen minutes per delivery and catch the majority of consumable problems while the carrier is still on site.
1. Packaging integrity
Check for crushed cartons, water staining and broken seals. Hermetically sealed electrode packaging is the primary moisture barrier; once it is compromised, the coating is already absorbing water.
2. Certificates against the order
The certificate should name the standard the product was manufactured and tested to, and match the batch numbers on the boxes. A certificate for a different heat or batch is not a certificate for this delivery.
3. Batch and heat numbers legible
If you cannot read the batch number, you cannot trace the material later. Photograph the labels before the packaging is opened and discarded.
4. Diameter and length
Measure a sample rather than reading the label. Tolerance is a manufacturing variable, and a diameter at the edge of tolerance changes the welding parameters the welder has been using.
5. Coating condition (electrodes)
Look for chipped coating, cracks along the length, and exposed core wire at the ends. A damaged coating arc is unstable and, on a low-hydrogen electrode, defeats the purpose of buying low-hydrogen in the first place.
6. Spool and winding condition (wire)
Check for edge damage on the spool, and for wire that has sprung or crossed on the layer. Both cause feed problems that will be blamed on the welding machine.
7. Surface condition of wire
The copper coating should be uniform. Rust spots, dark patches or a dull finish indicate either a coating problem or moisture exposure in transit.
8. Quantity against the packing list
Count cartons, not pallets. Discrepancies are easiest to resolve before the carrier leaves, and the claim is against the carrier rather than the supplier at that point.
9. Storage immediately after inspection
Consumables that pass inspection and are then left in an open yard have failed by the following week. Move them to dry storage the same day, and log the date they were received.
10. Retain one unopened sample
Keep one sealed carton or one spool, labelled with the batch number and delivery date. If a problem surfaces weeks later, that sample is the evidence that decides the conversation with the supplier.